    After weeks of tidying up and remedial works the main platform is being rebuilt at Oswestry, currently the brick facing is in progress. There is a lot going on at the moment. See the blog for updates
    http://cambrianrailways.com/blog/

    and Dan's pages for some more photos.
    http://www.osrail.co.uk/

    These are in addiotion to the main web sites but offer more detailed news about progress.
     
  2. 8-10 Brass Cleaner

    8-10 Brass Cleaner Member

    Registriert seit:
    16 Juni 2006
    Beiträge:
    231
    Zustimmungen:
    0
    Beruf:
    Bridges
    I assume that someone has noticed that the trial panel had the snap headers every 5th row, whearas the permanent works seems only to have them every 6th (?) course?.

    I would hate it for you to have to take it down and rebuild it consistent with the approved panel.
     
  3. Coboman

    Coboman Member

    Registriert seit:
    27 Juli 2010
    Beiträge:
    534
    Zustimmungen:
    4
    Ort:
    GNR Outpost
    Would somebody translate that into newbielish as I have no idea what it means! ;)
    Jim
     
  4. ilvaporista

    ilvaporista Part of the furniture

    Registriert seit:
    16 Januar 2006
    Beiträge:
    4.356
    Zustimmungen:
    5.455
    Geschlecht:
    männlich
    Beruf:
    C.Eng
    Ort:
    On the 45th!
    A header is the view end on of a brick. When laying a double skin wall these headers lock the two walls together. A stretcher is the side on,normal view, of a brick. In this case the wall is single skin so is for appearance only.
     
  5. Coboman

    Coboman Member

    Registriert seit:
    27 Juli 2010
    Beiträge:
    534
    Zustimmungen:
    4
    Ort:
    GNR Outpost
    Thanks! Now i understand ;)
     
  6. ilvaporista

    ilvaporista Part of the furniture

    Registriert seit:
    16 Januar 2006
    Beiträge:
    4.356
    Zustimmungen:
    5.455
    Geschlecht:
    männlich
    Beruf:
    C.Eng
    Ort:
    On the 45th!
  7. Martin Perry

    Martin Perry Nat Pres stalwart Staff Member Moderator Friend

    Registriert seit:
    15 April 2006
    Beiträge:
    16.551
    Zustimmungen:
    7.897
    Ort:
    1012 / 60158
    Heritage Railway Volunteer:
    Yes I am an active volunteer
  8. Sidmouth

    Sidmouth Resident of Nat Pres Staff Member Moderator

    Registriert seit:
    12 September 2005
    Beiträge:
    10.146
    Zustimmungen:
    9.777
    Geschlecht:
    männlich
    Ort:
    Alderan !
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    the real tragedy when you look at the picture is what has been lost , The other (down ?) platform buildings , Footbridge , canopies , Signaling , through road

    When you think how long the Oswestry scheme has been around and finally the shoots of growth are emerging to make a fully fledged railway . The sad thing in a way is the preservation boat has been missed in terms of Barry and appropriate stock . Will Foxcote maybe return ?
     
  9. Gav106

    Gav106 Well-Known Member

    Registriert seit:
    29 März 2010
    Beiträge:
    1.772
    Zustimmungen:
    2.170
    Ort:
    Nantwich, Cheshire
    I know what you mean there. It could have been one of the most amazing heritage railways in the uk with the size of Oswestry station/engine shed/works but due to a no. of incidents over the years it doesnt seem to have progressed much. its quite local to me and i would love for things to progress. I understand that the two groups are now working together (maybe this is one of the reasons things havent progressed. Im only quoting from what i have read in magazines about them faling out). I keep looking at osrail and cambrian railways blog to see the updates.

    Maybe when things progress Cogan hall may return from the llangollen? you never know who may win the lottery and buy up a loco. haha
     
  10. 8-10 Brass Cleaner

    8-10 Brass Cleaner Member

    Registriert seit:
    16 Juni 2006
    Beiträge:
    231
    Zustimmungen:
    0
    Beruf:
    Bridges
    There are still major obstacles to overcome.

    I'm told that the old bridge near the gasworks site has some propping underneath it that would preclude the passage of trains, so trains from Oswestry will not be able to get towards Llynclys etc.
     
  11. ilvaporista

    ilvaporista Part of the furniture

    Registriert seit:
    16 Januar 2006
    Beiträge:
    4.356
    Zustimmungen:
    5.455
    Geschlecht:
    männlich
    Beruf:
    C.Eng
    Ort:
    On the 45th!
    The bridge at the South will need strengthening to allow the current temporary supports to be removed. This is part of the overall plan, first objective is to operate trains to the bridge to demonstrate that real progress is being made.

    The major obstacles are credibility and money, both of these are being worked on. The two main groups are working to a common agenda. The money is needed to make further progress but as seen by progress on the platform things are starting to move.
     
  12. buseng

    buseng Part of the furniture

    Registriert seit:
    9 September 2005
    Beiträge:
    4.801
    Zustimmungen:
    349
    Geschlecht:
    männlich
    Beruf:
    Retired
    Ort:
    Tilehurst, Reading, Berks.
  13. ilvaporista

    ilvaporista Part of the furniture

    Registriert seit:
    16 Januar 2006
    Beiträge:
    4.356
    Zustimmungen:
    5.455
    Geschlecht:
    männlich
    Beruf:
    C.Eng
    Ort:
    On the 45th!
  14. ilvaporista

    ilvaporista Part of the furniture

    Registriert seit:
    16 Januar 2006
    Beiträge:
    4.356
    Zustimmungen:
    5.455
    Geschlecht:
    männlich
    Beruf:
    C.Eng
    Ort:
    On the 45th!
    Platform edging now going on, can't wait to see it finished with a train standing at the platform for the first time in many years
    See the pictures
    http://cambrianrailways.com/blog/
     
  15. Coboman

    Coboman Member

    Registriert seit:
    27 Juli 2010
    Beiträge:
    534
    Zustimmungen:
    4
    Ort:
    GNR Outpost
    *Your doing a cracking job there lads. Get Tommy Walsh in to a challenge and help you get it finnished ;)
     
  16. osrail

    osrail New Member

    Registriert seit:
    27 September 2010
    Beiträge:
    22
    Zustimmungen:
    1
    Geschlecht:
    männlich
    Ort:
    Caernarfon / Oswestry
    Hi everyone, i have updated my site so you can see the latest developments in Oswestry.


    Link
     
  17. ilvaporista

    ilvaporista Part of the furniture

    Registriert seit:
    16 Januar 2006
    Beiträge:
    4.356
    Zustimmungen:
    5.455
    Geschlecht:
    männlich
    Beruf:
    C.Eng
    Ort:
    On the 45th!
  18. Martin Perry

    Martin Perry Nat Pres stalwart Staff Member Moderator Friend

    Registriert seit:
    15 April 2006
    Beiträge:
    16.551
    Zustimmungen:
    7.897
    Ort:
    1012 / 60158
    Heritage Railway Volunteer:
    Yes I am an active volunteer
  19. ilvaporista

    ilvaporista Part of the furniture

    Registriert seit:
    16 Januar 2006
    Beiträge:
    4.356
    Zustimmungen:
    5.455
    Geschlecht:
    männlich
    Beruf:
    C.Eng
    Ort:
    On the 45th!
  20. osrail

    osrail New Member

    Registriert seit:
    27 September 2010
    Beiträge:
    22
    Zustimmungen:
    1
    Geschlecht:
    männlich
    Ort:
    Caernarfon / Oswestry
    I took a walk last week between Porth-Y-Waen Halt and the end of the line ad Llanddu.