Yes it did a 100mph test run and supposedly without problems during or subsequently, as a result of which Tornado was 'passed' for 90mph. A later...
Experience yes, ability..... hmmm
That may well be, my question is but how short of motive power would WCR have to be before they approached LSL for one of theirs? and how...
If a Clan wasnt suitable for the Mallaig road then Tangers certainly isnt... looks like LSL have a black 5 and at a push a B1... ah, so.
The ones who truly want failure see that something is amiss and yet say nothing...
Yes thats more likely, as the Bond issue to cover it ( with contingency) was £ 500k. Just stumbled across this which is interesting;
IIRC ( and its very hazy) The first one was £ 300,000 and the pair were < £ 500,000 each...
and who for...
Would point out that this feature also exists on the Caprotti Standard 5, but i dont believe that there are surviving drawings....
Well LSL might like an A1 and/or need some spares for Blue Peter..
A1SLT - Prince of Wales (a1steam.com) PRINCE OF WALES Building Britain’s most powerful steam locomotive – come and join us! MAKE A DONATION...
Here 's a question, so when this new boiler is finished, with a water space suited to its make up and a reduced grate area of, lets say 5% which i...
AFAIR Meiningen ' dont do copper' . I dont remember whether the decision to go steel was done before the supplier was selected or as part of the...
Given the propulsion problems not perhaps an auspicious association...
Away from the somewhat depressing nitty gritty... how about a Name Change ! nothing drastic, but should now be considering 'Princess of Wales '...
In a conversation with one of Tornados support team ( a fitter) at the NYM it came up that Meiningen view boilers as a ' consumable' and the...
Interesting, but if boiler #2 is supposedly different internally why does it have exactly the same stay pattern as boiler#1 -For all you so...
Hindsight is a marvellous thing, So the plan was to put the original boiler at the back of the production line and put a new firebox in it. But...
Rather than allow Meiningen to redesign the firebox / waterspaces/ foundation ring to suit their guideline values and construction methods it was...
So if the new boiler was ready to be tubed in September, and given that the Germans have forgotten how to tube a boiler to our accepted practices...