    Another update posted a couple of days ago...
    http://www.gcrailway.co.uk/unify/
     
    aron33, jnc, J Rob't Harrison și alți 4 apreciază asta.
  2. seawright

    seawright New Member

    Înscris:
    30 Sep 2012
    Mesaje:
    169
    Aprecieri primite:
    26
    The article in the Rail Engineer states that speeds of up to 75mph are allowed for testing purposes. Is this correct, as I was under the impression that the dispensation only allowed speeds of up to 60mph?
     
  3. pwsw5054

    pwsw5054 Member

    Înscris:
    5 Ian 2016
    Mesaje:
    411
    Aprecieri primite:
    1.284
    Sex:
    Masculin
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    I think it's 60 for steam

    Sent from my SM-A310F using Tapatalk
     
  4. Raimondo

    Raimondo New Member

    Înscris:
    24 Oct 2005
    Mesaje:
    135
    Aprecieri primite:
    116
    Yep, I understand it's 60mph for steam and 75mph for diesels.

    Here's a video of the Peak D123 doing some 75mph brake testing...
     
    echap și 30854 apreciază asta.
  5. JWKB

    JWKB Member

    Înscris:
    17 Apr 2005
    Mesaje:
    421
    Aprecieri primite:
    95
    Morning All,
    I was wondering if there was anywhere that provided a breakdown of how much each of the elements of phase 1 had cost i.e Bridge, Abutments etc
    I have had a quick look at this thread and the offical website with no joy....
     
  6. John Webb

    John Webb Member

    Înscris:
    2 Mar 2010
    Mesaje:
    501
    Aprecieri primite:
    86
    Ocupație:
    Retired
    Locație:
    St Albans, Herts
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Bearing in mind commercial contractors are involved, I would think that such a breakdown might be considered as 'Commercial in Confidence' and unlikely to be put into the public domain. Out of curiosity what is your interest in such a breakdown of the costs?
     
    Black Jim apreciază asta.
  7. mogulb

    mogulb New Member

    Înscris:
    20 Dec 2010
    Mesaje:
    133
    Aprecieri primite:
    95
    I was wondering if there was anywhere that provided a breakdown of how much each of the elements of phase 1 had cost i.e Bridge, Abutments etc
    I have had a quick look at this thread and the offical website with no joy...

    James. Not seen anything that gives a total breakdown, which is not surprising as a full design has not been completed and all permissions , agreements etc are not yet in place.
    The bridge over the MML construction cost is just under £2m (from GCRs accounts) plus additional piling works. The bridge over the canal refurbishment has been costed at £400,000 and is subject to a recently launched appeal. Also a substantial sum has already been spent on surveys, design work, legal work etc etc.
     
  8. JWKB

    JWKB Member

    Înscris:
    17 Apr 2005
    Mesaje:
    421
    Aprecieri primite:
    95
    Evening,

    The reason was just pure curiosity on my part about the cost of physically constructing the steel deck and abutments. Over recent years many railways (NYMR, WHR, RVR) have built new bridges and it is just interesting to see what the replacement cost is compared to typical repair cost.


    James Buckley
     
  9. AndyY

    AndyY Member

    Înscris:
    23 Feb 2013
    Mesaje:
    433
    Aprecieri primite:
    480
    Given that the bridge was completely missing there was only one option in this case!
     
  10. MellishR

    MellishR Resident of Nat Pres Friend

    Înscris:
    16 Apr 2009
    Mesaje:
    8.911
    Aprecieri primite:
    5.847
    But on the other hand there was a second-hand deck available.
     
  11. Bean-counter

    Bean-counter Part of the furniture

    Înscris:
    21 Iul 2007
    Mesaje:
    5.844
    Aprecieri primite:
    7.688
    Sex:
    Masculin
    Locație:
    Former NP Member
    Heritage Railway Volunteer:
    No I do not currently volunteer
    In some respects, this would be cheaper - no old deck to get out of the way first! However, I believe the abutments needed at least major work if not building from scratch on one side, so it is 'swings and roundabouts'.

    The actual beams and decking units can be quite 'cheap' (I seem to recall the basic beams for Bridge 30 were under £100k but were probably around 10% of the total project costs including associated trackwork). In this case, installation would be the main cost I suspect - not least NwR possessions.

    I was once told by someone who knows that certain bridges were just 'little bridges - around £100k to replace'!

    Steven
     
    Black Jim și Bluenosejohn apreciază asta.
  12. AndyY

    AndyY Member

    Înscris:
    23 Feb 2013
    Mesaje:
    433
    Aprecieri primite:
    480
    True, but not long enough to reach across in one span, and the second-hand decks are planned to be used on the 'gap' job anyway.
     
    jnc apreciază asta.
  13. AndyY

    AndyY Member

    Înscris:
    23 Feb 2013
    Mesaje:
    433
    Aprecieri primite:
    480
    As a further observation, I understand that once the bridge is complete it will be handed over to Network Rail who will then take on responsibility for its maintenance. Having a new bridge to a NR standard design therefore makes sense.
     
    W.Williams, aron33, CH 19 și alți 4 apreciază asta.
  14. mikechant

    mikechant Member

    Înscris:
    24 Oct 2012
    Mesaje:
    225
    Aprecieri primite:
    243
    The GCR is very much on the ball as far as fundraising. There is a specific £475,000 appeal now for the canal bridge to be restored this Autumn and inspired by the reality of the Midland Mainline bridge installation I have just made a substantial donation (>1/1000 of the cost). This is not to boast (I'm very lucky to be in this position due to an inheritance) but to encourage others who can afford to donate to do so. This project can come to fruition sooner rather than later if the donations keep flowing.
     
    David R, Black Jim, desperado și alți 8 apreciază asta.
  15. Railboy

    Railboy New Member

    Înscris:
    10 Dec 2016
    Mesaje:
    166
    Aprecieri primite:
    238
    Sex:
    Masculin
    Locație:
    Hamburg
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Here I will share to you one of the most recent videos of the GCR concerning the planning and the future developments required for reunification.


    It's really interesting to see they use the world wide (I think I have to exlude to somehow the states, because they're still performing well in their way of exeptionalism) understandable SI system (metric system) in most of the given information and probably also for construction, although they give the total length in nostalgic miles. For every engineer it's real headache but at least we do now have the information how the whole embankment will look like in about a decade time(or maybe even a bit less).

    Cheers!
     
    deaftech, CH 19, J Rob't Harrison și alți 5 apreciază asta.
  16. Johann Marsbar

    Johann Marsbar Well-Known Member

    Înscris:
    21 Feb 2016
    Mesaje:
    1.669
    Aprecieri primite:
    2.178
    Sex:
    Masculin
    Locație:
    Suffolk
    Heritage Railway Volunteer:
    No I do not currently volunteer
    J Rob't Harrison, Tuska și TommyD apreciază asta.
  17. Johann Marsbar

    Johann Marsbar Well-Known Member

    Înscris:
    21 Feb 2016
    Mesaje:
    1.669
    Aprecieri primite:
    2.178
    Sex:
    Masculin
    Locație:
    Suffolk
    Heritage Railway Volunteer:
    No I do not currently volunteer
  18. Johann Marsbar

    Johann Marsbar Well-Known Member

    Înscris:
    21 Feb 2016
    Mesaje:
    1.669
    Aprecieri primite:
    2.178
    Sex:
    Masculin
    Locație:
    Suffolk
    Heritage Railway Volunteer:
    No I do not currently volunteer
    The latest edition of the FoGCML magazine Main Line, which arrived yesterday, has a 3 page article on the changes necessary to link the "Gap" section to Loughborough station, including a rebuilt loco shed/workshops on its existing location. Looks like double track is planned to extend north of the canal bridge area, passing by the shed on its western side .
     
    Last edited: 4 Mar 2018
    Black Jim și J Rob't Harrison apreciază asta.
  19. Johann Marsbar

    Johann Marsbar Well-Known Member

    Înscris:
    21 Feb 2016
    Mesaje:
    1.669
    Aprecieri primite:
    2.178
    Sex:
    Masculin
    Locație:
    Suffolk
    Heritage Railway Volunteer:
    No I do not currently volunteer
    David R, Black Jim, jnc și încă o persoană apreciază asta.
  20. mikechant

    mikechant Member

    Înscris:
    24 Oct 2012
    Mesaje:
    225
    Aprecieri primite:
    243
    'Match funding March' for the canal bridge fund is drawing to a close, I've just donated and with gift aid *and* match funding my donation is worth about 2.5x the amount I paid. Get in there now, 2 days to go!
     

Distribuie pagina asta