Construction of 3' Gauge Blyth for Southwold Railway Trust by NBR Engineering, Darlington

Rasprava u 'Narrow Gauge Railways' pokrenuta od David Humphreys, 16. Svibanj 2019..

  1. ghost

    ghost Part of the furniture

    Pridružen(a):
    29. Svibanj 2006.
    Poruka:
    4,341
    Lajkova:
    5,850
    Spol:
    Muškarac
    Grad:
    N.Ireland
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    This was discussed previously and if I recall correctly, the new frames are in fact thicker than the original loco. 5/8 original vs 20mm new I seem to remember.

    Keith
     
  2. Johann Marsbar

    Johann Marsbar Well-Known Member

    Pridružen(a):
    21. Veljača 2016.
    Poruka:
    1,671
    Lajkova:
    2,192
    Spol:
    Muškarac
    Grad:
    Suffolk
    Heritage Railway Volunteer:
    No I do not currently volunteer
  3. Johann Marsbar

    Johann Marsbar Well-Known Member

    Pridružen(a):
    21. Veljača 2016.
    Poruka:
    1,671
    Lajkova:
    2,192
    Spol:
    Muškarac
    Grad:
    Suffolk
    Heritage Railway Volunteer:
    No I do not currently volunteer
  4. David Humphreys

    David Humphreys New Member

    Pridružen(a):
    11. Travanj 2011.
    Poruka:
    99
    Lajkova:
    306
    Spol:
    Muškarac
    Grad:
    Boosbeck, Saltburn by the Sea
    Heritage Railway Volunteer:
    No I do not currently volunteer
    If people want to follow the construction more closely, along with the other new build 1863 Mountaineer and other locomotive components and boiler constructions, please like and follow North Bay Railway Engineering Services on Facebook.
     
  5. David Humphreys

    David Humphreys New Member

    Pridružen(a):
    11. Travanj 2011.
    Poruka:
    99
    Lajkova:
    306
    Spol:
    Muškarac
    Grad:
    Boosbeck, Saltburn by the Sea
    Heritage Railway Volunteer:
    No I do not currently volunteer
    The wheels are now on site and will be fitted in the next few days. The completed chassis with axle boxes is on the lift behind. Cylinders finished and finished front and back covers present too.

    The wheels will have their crank pins shrunk in and after painting in Great Eastern Blue and the chassis is turned over, it will then be a rolling chassis. Once the brake hangers and pull rods fitted, phases 2& 3 will be finished and we moee onto the motion - phase 4. It is hoped that we will have an air run chassis in the Summer. The boiler was finished last year.

    Southwold Railway Trust are still looking for funding and with your help, the locomotive could be in steam this time next year https://www.southwoldrailway.co.uk/trust-projects/2-4-0t-no-3-blyth/

    [​IMG]
     
    Goldie, Paul42, Meiriongwril i 10 ostalih se sviđa ovo.
  6. StoneRoad

    StoneRoad Member

    Pridružen(a):
    29. Listopad 2009.
    Poruka:
    979
    Lajkova:
    389
    Interesi:
    Restoration of heritage items, mainly in timber.
    Grad:
    Haltwhistle
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    All good progress there, I'm pleased to see !
     
  7. David Humphreys

    David Humphreys New Member

    Pridružen(a):
    11. Travanj 2011.
    Poruka:
    99
    Lajkova:
    306
    Spol:
    Muškarac
    Grad:
    Boosbeck, Saltburn by the Sea
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Blyth has been turned the right way up and moved into the position in the workshop where it will be finished.

    Connecting rods and a couple rods are finished and the eccentrics and straps are on site and being processed. Running boards have been added.

    The valve train together with reversing lever and Di block are currently being manufactured.

    The steam power brake has been fitted and the handbrake mechanism is almost complete.

    The piston/Slide bars are on site and complete and the valve mechanism is in the process of being made.

    At the current rate of build, it is hoped to run the locomotive on compressed air in the autumn. The boiler that was made last year will then be added and we will start on the manufacture of the tanks and cab.

    The Trust are undertaking a final push on fundraising to hopefully finish the locomotive in 2021. https://www.southwoldrailway.co.uk/trust-projects/2-4-0t-no-3-blyth/
     
    Goldie, 30854, ilvaporista i 4 ostalih se sviđa ovo.
  8. ghost

    ghost Part of the furniture

    Pridružen(a):
    29. Svibanj 2006.
    Poruka:
    4,341
    Lajkova:
    5,850
    Spol:
    Muškarac
    Grad:
    N.Ireland
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    I've been following the build on the NBRE Facebook page. Keep up the great work.

    Keith
     
    Devonbelle and David Humphreys like this.

Podijelite ovu stranicu