Rother Valley Railway

Discussion in 'Heritage Railways & Centres in the UK' started by nine elms fan, Nov 4, 2012.

  1. Miff

    Miff Part of the furniture Friend

    Joined:
    Jun 17, 2008
    Messages:
    3,279
    Likes Received:
    3,573
    I think Fireline’s post shows it’s rather more than the paperwork. There’s also ballasting & tamping of the whole line.

    Installing & commissioning the signalling (both rail and road) for 3 level crossings, plus a passing loop and a terminus station, is a substantial enough project in itself.
     
    clinker, Steve, H Cloutt and 4 others like this.
  2. Flying Phil

    Flying Phil Part of the furniture

    Joined:
    Dec 10, 2018
    Messages:
    3,189
    Likes Received:
    7,094
    Gender:
    Male
    Location:
    Leicestershire
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    It is good to get the regular updates and see the steady progress of this project - Well Done to all involved.
     
    clinker, Hawkeye28, H Cloutt and 5 others like this.
  3. hyboy

    hyboy New Member

    Joined:
    Feb 16, 2012
    Messages:
    142
    Likes Received:
    149
    Gender:
    Male
    Location:
    Bristol
    Heritage Railway Volunteer:
    No I do not currently volunteer
    I have clearly missed my cue by a couple of days but regarding that road and rail interaction... Every Concorde produced in Bristol ( Brabazon Hangars) had to negotiate the Filton to Hallen railway level crossing to reach the runway in Gloucestershire. The crossing probably had the longest ' gates ' in the country , actually wheeled barriers.
     
    clinker, Wenlock, CH 19 and 4 others like this.
  4. jnc

    jnc Well-Known Member

    Joined:
    Apr 3, 2012
    Messages:
    1,797
    Likes Received:
    3,140
    Gender:
    Male
    Location:
    Western Atlantic
    Heritage Railway Volunteer:
    No I do not currently volunteer
    And here is the promised track laying visual summary:

    Section 5c Overview - 6 Aug 26

    The plain images (in addition to the several pan- and zoom-able images) are worth enlarging; lots of interesting details to be seen there (e.g. stacked track-laying supplies, at the bottom of the top image).

    Of particular interest was the one captioned "The farmer has easy access North (right) and South (left) of the track by this culvert build", showing a crossing constructed from old ties to allow easy crossing of the track by large vehicles. After the farmer (understandably, from their point of view) put up considerable resistance to the substantial inconvenience (to them) of a rail line being re-laid across their fields, reducing their easy access to those on the far side of it, I am glad to see that the RVR has apparently moved past any residual upset at that resistance, and is taking some steps to reduce that inconvenience (even if some residual inconvenience unavoidably remains) - although of course such measures may have been committed to as part of getting the permission to reinstate the line. I do hope the measures installed are adequate to reduce the inconvenience as much as practicable, and that every consideration will be given to installing all practicable such measures.

    Noel
     
    Last edited: Aug 28, 2026 at 6:47 PM
    Hirn, CH 19, banburysaint and 4 others like this.
  5. mikehartuk

    mikehartuk New Member

    Joined:
    Jun 29, 2007
    Messages:
    180
    Likes Received:
    975
    Gender:
    Male
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    [
     
    Last edited: Aug 28, 2026 at 8:55 AM
  6. mikehartuk

    mikehartuk New Member

    Joined:
    Jun 29, 2007
    Messages:
    180
    Likes Received:
    975
    Gender:
    Male
    Heritage Railway Volunteer:
    Yes I am an active volunteer
  7. mikehartuk

    mikehartuk New Member

    Joined:
    Jun 29, 2007
    Messages:
    180
    Likes Received:
    975
    Gender:
    Male
    Heritage Railway Volunteer:
    Yes I am an active volunteer
  8. mikehartuk

    mikehartuk New Member

    Joined:
    Jun 29, 2007
    Messages:
    180
    Likes Received:
    975
    Gender:
    Male
    Heritage Railway Volunteer:
    Yes I am an active volunteer
  9. lynbarn

    lynbarn Well-Known Member

    Joined:
    Aug 22, 2006
    Messages:
    2,012
    Likes Received:
    747
    Gender:
    Male
    Occupation:
    Retired
    Location:
    Kent
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Oh no, the blog pages are down, and I am getting withdrawal symptoms already :Nurse: . Still, the guy behind them needs a break just as much as the rest of us, so enjoy the bank holiday, and I look forward to the update as and when it appears. Now to keep an eye on Facebook :D
     
    clinker and jnc like this.
  10. H Cloutt

    H Cloutt Well-Known Member

    Joined:
    Dec 22, 2018
    Messages:
    1,095
    Likes Received:
    1,609
    Gender:
    Male
    Location:
    Battle
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Just seen a new post on the blog here.

    This gives details of section 5b. The trackbed is ready for track to be laid.

    Further update on Section 5a just posted.
     
    Last edited: Aug 31, 2026 at 5:01 PM
  11. jnc

    jnc Well-Known Member

    Joined:
    Apr 3, 2012
    Messages:
    1,797
    Likes Received:
    3,140
    Gender:
    Male
    Location:
    Western Atlantic
    Heritage Railway Volunteer:
    No I do not currently volunteer
    That one, "Section 5b, Section overview - 1", has been added to with another, Section 5a Section overview.

    I seem to recall reading somewhere that there was hope that the ballast needed to underlay the track could be brought in by rail (obviously a good idea for an extremely large, heavy load). That would of course need the level crossings at the A21 and Northbridge Street (even if manually signaled during the construction phase): the latter is of course already in, but does anyone know if an approximate data for the installation of the former has been posited?

    PS: Never mind! I just saw @Miff's post, indicating "the A21 crossing hoped for in the spring of '27".

    Noel
     
    Last edited: Aug 31, 2026 at 5:50 PM
    Miff and H Cloutt like this.