North Yorkshire Moors Railway General Discussion

Discussion in 'Heritage Railways & Centres in the UK' started by The Black Hat, Feb 13, 2011.

  1. Jark91

    Jark91 Member

    Joined:
    Dec 26, 2009
    Messages:
    280
    Likes Received:
    101
    How long would works on the scale of Bridge 42 usually take? Less than 3 months (if they plan to reopen fully in time for easter) sounds quick.
     
  2. Sulzerman

    Sulzerman Member

    Joined:
    Jan 22, 2025
    Messages:
    287
    Likes Received:
    451
    Gender:
    Male
    Location:
    Malton
    Heritage Railway Volunteer:
    No I do not currently volunteer
    I doubt the bridge will be tackled. I thought work would be late 2027 for completion in 2028.
    It may be work on platform 4 at Grosmont and signalling for the NR connection will be this winter.
     
  3. 5944

    5944 Resident of Nat Pres

    Joined:
    Jan 14, 2006
    Messages:
    10,484
    Likes Received:
    13,038
    Gender:
    Male
    Occupation:
    Train Maintainer for GTR at Hornsey
    Location:
    Letchworth
    Heritage Railway Volunteer:
    No I do not currently volunteer
    I assume the line is shut now north of Goathland until Easter, so that gives them over 5 months to carry out the work. It's not going to be a quick job, especially not in the middle of potentially a very cold, snowy winter.

    Whether they can afford it is another matter...
     
    Paul42, silversteellady and Jark91 like this.
  4. 60044

    60044 Well-Known Member

    Joined:
    Feb 24, 2016
    Messages:
    1,736
    Likes Received:
    2,352
    Gender:
    Male
    Location:
    Salisbury
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    I've been told they are waiting for the result of a grant application, and if it comes through fairly soon the work will at least be started this winter - that could save another year of having to hire the props. A lot of the pway work needed is ballasting and tamping, which ought to be reasonably inexpensive cost of ballast mostly, and not starting from scratch, and the paid pway staff are at a minimum and being paid anyway.
     
  5. jnc

    jnc Well-Known Member

    Joined:
    Apr 3, 2012
    Messages:
    1,881
    Likes Received:
    3,244
    Gender:
    Male
    Location:
    Western Atlantic
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Going from my admittedly now-dim memories of what was outlined in the planning application for the work, it would to some degree depend on how big a crew was put onto the job; i.e. how much money they wanted to spend. I don't know enough about that kind of work to have a reliable sense of how to go from what was outlined in the planning application, to 'how long it would take'. Putting the propping up took, IIRC, several weeks; going from that, my guess for the repairs would be a month or two (depending on crew size).

    Noel
     
  6. Daddsie71b

    Daddsie71b Well-Known Member Friend

    Joined:
    Apr 4, 2013
    Messages:
    1,141
    Likes Received:
    1,020
    Gender:
    Male
    Location:
    34091
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    For one of the biggest heritage railways relying on grants to complete the works rings alarm bells. We are all maintaining ageing infrastructure and should be putting money aside.
     