    Bridges 24 & 25 are an absolute scandal. Heads should have rolled over them. For those that don't know, the decks are significantly higher than the originals. How such a failure of project management occurred is beyond my understanding.

    Sawdust.
     
    Sheff likes this.
  2. Steve

    Steve Nat Pres stalwart Friend

    Joined:
    Oct 7, 2006
    Messages:
    13,787
    Likes Received:
    14,847
    Occupation:
    Gentleman of leisure, nowadays
    Location:
    Near Leeds
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Heads did roll in that the civil engineer either resigned or was sacked. The official answer was resigned to pursue other interests.
    The track is on an embankment and there is not enough width to raise the level to match.
     
  3. Sawdust

    Sawdust Member

    Joined:
    Jul 18, 2015
    Messages:
    749
    Likes Received:
    1,323
    Gender:
    Male
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    It'll be expensive, but isn't the solution to lower the abutments, so the bridges are at the correct height?

    Sawdust.
     
  4. Lineisclear

    Lineisclear Well-Known Member

    Joined:
    May 24, 2020
    Messages:
    1,736
    Likes Received:
    1,590
    Gender:
    Male
    Location:
    Worcestershire
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    I believe the proposed remediation (which is a consequence of the initial contractor going bust) involves the building of retaining structures to secure additional ballast raising the track level either side of and between the two bridges?
     