70013 'Oliver Cromwell' repair update

Rasprava u 'Steam Traction' pokrenuta od Raimondo, 15. Studeni 2010..

  1. Raimondo

    Raimondo New Member

    Pridružen(a):
    24. Listopad 2005.
    Poruka:
    135
    Lajkova:
    116
    This has been posted today by the 5305LA boys on their website:

    "No. 70013 “Oliver Cromwell”, the NRM’s Britannia, is currently off duty and is still at LNWR Crewe Locomotive Works receiving attention to the firebox. We had hoped that the work would be completed by now and we would be busy putting the engine back together ready to take up her December work. The boiler work will probably be completed by the end of this month, but obviously there will be a lot of work afterwards to get the cladding and back head fittings replaced, the cab back on, and the boiler steam tested before she can return to traffic. Sadly we aren’t quite at a stage where we can be confident of getting the engine back together in time to take up her rostered duties in December. Therefore in fairness to the railtour operators and the travelling public we have decided to withdraw the engine from the trips in order that the operators have time to source an alternative locomotive, instead of keeping going and then having to withdraw at the last minute which might leave everyone in the lurch. We are very disappointed to have to make this decision, but it would be unprofessional of us to take any other action".

    A shame that the repair has dragged on but they are quite right to withdraw the loco from it's rostered duties, rather then letting people down.

    Hopefully 70013 will be back with us in the New Year, so good luck to the 5305LA team on the repair and thanks for keeping us in touch.
     
  2. Dan Hamblin

    Dan Hamblin Part of the furniture

    Pridružen(a):
    27. Ožujak 2006.
    Poruka:
    2,549
    Lajkova:
    190
    Interesi:
    Rolling Stock Engineer
    Grad:
    Kent
    Yes, a big shame indeed - can't help feeling sorry for the 5305LA. It also means that the much anticipated Steam Dreams double Britannia trips before Christmas will be just down to 70000 plus another.

    Regards,

    Dan
     
  3. Steve from GWR

    Steve from GWR Well-Known Member

    Pridružen(a):
    18. Veljača 2010.
    Poruka:
    1,292
    Lajkova:
    14
    Be nice to see 70000 and 71000 double heading!
     
  4. polmadie

    polmadie Well-Known Member

    Pridružen(a):
    27. Rujan 2007.
    Poruka:
    1,242
    Lajkova:
    472
  5. Steve from GWR

    Steve from GWR Well-Known Member

    Pridružen(a):
    18. Veljača 2010.
    Poruka:
    1,292
    Lajkova:
    14
  6. 6:05 special

    6:05 special Well-Known Member Loco Owner

    Pridružen(a):
    20. Rujan 2006.
    Poruka:
    1,122
    Lajkova:
    6
    Grad:
    Merseyside
    This will not happen in the forseeable future as Steam Dreams operating company for the trains on 22 December is West Coast Railways 71000 is not currently operated by West Coast.
     
  7. Tim Fenton

    Tim Fenton New Member

    Pridružen(a):
    15. Studeni 2010.
    Poruka:
    90
    Lajkova:
    0
    Grad:
    Crewe
    One thing that may have slowed down 70013's repair is that the Heritage Centre has been busy with work recently.

    Apart from 70000, Clan Line has been in, 6100 has been finished (I think) - it's outside now, but not coupled to its tender, and AFAIK 60009 is being repaired too.

    I suspect they can't do too many things at once!
     
  8. bongo jim

    bongo jim New Member

    Pridružen(a):
    17. Kolovoz 2009.
    Poruka:
    32
    Lajkova:
    1
    Well if you cant do the job, why take it on in the first place?
    There does seem to be a lot of engines just hanging around and nothing happening at crewe.
     
  9. ADB968008

    ADB968008 Guest

    Depends if everyone else is busy, LNWR may have the shorter queue ?
     
  10. saltydog

    saltydog Part of the furniture

    Pridružen(a):
    31. Srpanj 2008.
    Poruka:
    2,566
    Lajkova:
    70
    Spol:
    Muškarac
    Interesi:
    Retired
    Grad:
    Birmingham
    70000,70013,6100,60009 and Clan Line. Seems to me that there's a lot happening at Crewe.
    It may have escaped your notice but it takes time to overhaul/repair a steam loco. It isn't a case of if you can't do the job, more a case of doing the job properly.....and that takes time.
     
  11. Matt35027

    Matt35027 Well-Known Member

    Pridružen(a):
    16. Listopad 2009.
    Poruka:
    1,122
    Lajkova:
    143
    Spol:
    Muškarac
    Interesi:
    Builder
    Grad:
    Near 74D
    Heritage Railway Volunteer:
    No I do not currently volunteer
    And 80136 is there and numerous boilers under repair.
     
  12. keith6233

    keith6233 Member

    Pridružen(a):
    21. Travanj 2006.
    Poruka:
    601
    Lajkova:
    184
    Interesi:
    Engineer
    Grad:
    Manchester
     
  13. RalphW

    RalphW Nat Pres stalwart Staff Member Administrator Friend

    Pridružen(a):
    11. Rujan 2005.
    Poruka:
    36,453
    Lajkova:
    9,914
    Spol:
    Muškarac
    Interesi:
    Retired-ish, Part time rail tour steward.
    Grad:
    Northwich
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Could the reason that there are quite a few locos there be anything to do with the quality of their workmanship. If they are perceived as one of the best places to get your overhauls done, then a lot of work is the result.
     
  14. williamfj2

    williamfj2 Member

    Pridružen(a):
    21. Prosinac 2007.
    Poruka:
    637
    Lajkova:
    56
    Spol:
    Muškarac
    Grad:
    50A
    There's also one of the WHR garratts and 80136 is there I think.
     
  15. Tim Fenton

    Tim Fenton New Member

    Pridružen(a):
    15. Studeni 2010.
    Poruka:
    90
    Lajkova:
    0
    Grad:
    Crewe
    Ralph is spot on. The HC do tend to get stuff done properly. I was impressed at how rapidly they went from having Britannia's boiler steamed outside, to putting the loco together and getting it out on the main line.

    Also of course overhauling and restoring steam locos is an inexact science. It's not exactly like booking your car in for a service. Most likely that when 70013 arrived, it was expected to be started sooner than it has been. The loco AFAIK is now "inside" and so I expect it's being worked on. But a firebox crack needs to be repaired with no small measure of care.

    --
    Tim
    http://tim-fenton.fotopic.net/
    http://zelo-street.blogspot.com/
     
  16. Big Dave

    Big Dave Member

    Pridružen(a):
    17. Prosinac 2006.
    Poruka:
    466
    Lajkova:
    26
    Spol:
    Muškarac
    Interesi:
    Retired
    Grad:
    Bewdley
    Crewe are also doing 6634's boiler which the SVR will need in order to complete this loco. I would suggest that they have a lot of jobs on hand and so are doing well.
     
  17. bongo jim

    bongo jim New Member

    Pridružen(a):
    17. Kolovoz 2009.
    Poruka:
    32
    Lajkova:
    1
    Theres certainly a lot of engines there kevin but what will become of them all?
    will 6100 ever be finished in its current boiler ticket, apparently it now has a broken cylinder cover that has only taken 18 months to be noticed. still its hardly the end of the world after all 6115 had 2 new cyl covers and most of its inside cylinder and motion rebuilt in a few weeks, so if there as good as they like it to be put about at crewe im sure we'll see 6100 out and about in a couple of weeks?
    As for an earlier post i would hardly say that 6-7 months after the boiler was lifted in to put what was effectively a complete engine back togeather was impressive stuff, there are several other outfits that have done this in less than 2 weeks!
    Lets wait and see.
     
  18. saltydog

    saltydog Part of the furniture

    Pridružen(a):
    31. Srpanj 2008.
    Poruka:
    2,566
    Lajkova:
    70
    Spol:
    Muškarac
    Interesi:
    Retired
    Grad:
    Birmingham
    Don't forget that there are only three major loco works in the country......Crewe, Riley's and Tyseley and they all have a long list of work that they are undertaking, the owners who give them the contracts seem to understand more than you do that they have to wait their turn in the queue.
    Also would you care to name the 'outfits' that you claim have dropped a boiler back in the frames and miraculously managed to turn out a finished engine two weeks later?
    Oh of course!!! I was forgetting Swindon Works, Crewe Works, Doncaster Works and Eastleigh Works.
    bongo....now where have I seen that name before?
     
  19. Steve

    Steve Resident of Nat Pres Friend

    Pridružen(a):
    7. Listopad 2006.
    Poruka:
    12,738
    Lajkova:
    11,856
    Interesi:
    Gentleman of leisure, nowadays
    Grad:
    Near Leeds
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Didn't Riley's do something like that with 45407 earlier this year?

    And aren't they carrying out some rectification work on 70000, at the moment? Just wonder why that would be?

    Doesn't the Flour Mill do contract overhauls, as well?
     
  20. Bulleid Pacific

    Bulleid Pacific Part of the furniture

    Pridružen(a):
    14. Travanj 2007.
    Poruka:
    4,030
    Lajkova:
    1,089
    Interesi:
    A Thingy...
    I think its time we took a step back from the 'my loco works is better than yours' argument that seems to be developing here and return to progress on 70013.
     