If you register, you can do a lot more. And become an active part of our growing community. You'll have access to hidden forums, and enjoy the ability of replying and starting conversations.

Memoirs of a Railway Volunteer - Part 5

Discuție în 'Bullhead Memories' creată de sleepermonster, 10 Iul 2008.

  1. sleepermonster

    sleepermonster Member

    Înscris:
    19 Iun 2007
    Mesaje:
    953
    Aprecieri primite:
    1.094
    The Early Years at Darley Dale – Part III

    At about the same time as the first steam run to Matlock, we began laying track
    in the Up platform at Darley Dale. First the trackbed was scraped down below
    sleeper bottom level, and the chairs and small components spread out along the
    platform top. The last of the new sleepers, 130 or so, were laid out and
    chaired up, together with the best sleepers we could find at Hams Hall to
    complete the length. Tracklaying end on into a confined space is usually
    difficult, and this was worse than usual. There were coaches in the Down
    platform already, and no rail access over the crossing, even for works trains.
    We couldn’t get a JCB in because of the sleepers. There was only one method
    left, so we carried the rails in by hand across Station Road.

    This involved getting everyone on site in pairs with the rail tongs, balancing
    the rail on a small steel workshop bogie in the entrance to the South Yard, and
    dashing across the road when the coast was clear. Well, you try dashing with a 40’ rail. We set a block of wood against
    the kerb on the far side to protect the concrete, and with a little luck, the
    rail would lift up and skid over the top. I believe we tended to use 40’ rather
    than 60’rails here, not surprising really!

    By the beginning of February this new track had been extended beyond the end of
    the platform and had been very carefully lined and levelled, to use as a guide
    for the reconstruction of the Midland section of the Up platform.

    The first step in this work was to remove the coping stones. The method was to
    hammer a couple of fat chisels into the gap under the each coping to raise it
    slightly. About five men with crowbars could then get a good purchase, and flip
    the stone backwards onto rollers, short lengths of scaffolding tube which
    enabled the coping to be rolled back, clear of the platform edge. Then the wall
    could be taken down, and the stones laid out in courses on the track. Behind the
    wall was a mass of rubble bonded with black mortar, which had largely perished,
    and all the loose stone and general rubbish had to be raked out and shovelled
    onto the platform top. After a new foundation had been cast where necessary,
    the platform wall was remade, and the void behind filled with concrete and
    stone. In the process we raised the height of the platform edge by five inches,
    and set it back slightly.

    In fact raising the platform saved quite a lot of work, as when the time came to
    tarmac the platform top, we simply added a new layer over the old, which was in
    a poor state. We were also digging trenches for drains and to put in the
    electricity supply to the lamp posts, which were salvaged from a goods yard in
    Nottingham. There were plenty of crossing timbers which were not quite good
    enough to use in the track, and these were accurately laid out at the rear of
    the platform as a rear kerb and a guide for the Midland pattern fence. Beyond
    the platform, the tracks were being linked to the North Crossover and the
    carriage siding.

    Through the spring these works built up to a climax known as “The Day of the
    Mega Shunt”. Various rolling stock acquisitions and deliveries had led to the
    South Yard becoming very crowded once again. Over the years I have formulated a
    theory, the Oaks Law of Siding Capacity, which is that the time taken to shunt
    increases exponentially if sidings are more than 75% full, and that one siding
    in each group should be kept empty at all times. However we had managed to get
    our sticky fingers on all sorts of desirable goodies, and I was as responsible
    for the congestion as anyone. Derby Branch had financed the purchase of a
    Salmon bogie rail carrying wagon from Tinsley, something which Mick and I
    wanted very badly. The company had bought a tamper, I think from the Derby test
    centre, and this was receiving a lot of love and attention from Andy Lynch, Mick
    and others. Andrew Bodden had bought a 15 ton diesel crane, with various short
    flat trucks. On top of this, we had evacuated the remaining rolling stock from
    Buxton site as theft and vandalism were becoming too much of a problem. The 8F
    and its support coach were now in the south yard, along with all the turntable
    components. One reason for getting the extra freight stock was so that
    materials could be loaded onto wagons and kept mobile.

    The first of the crossing gates was easy to hang, with the diesel crane sat
    inside the south yard. Mick welded the steel mesh onto it, we painted it white
    and it looked very nice. To hang the second, the crane would need to be in the
    middle of Station Road, and the paradox was that we couldn’t use the level
    crossing until it had been completed and approved by HMRI. The solution was to
    book a days road closure, for Sunday 28th May. To make things more interesting,
    I had secured the donation of another four wagons from Chesterfield Cylinders,
    which I had been keeping an eye on for ten years and which suddenly became
    available. These were delivered on the Friday before the move took place.

    The imminent shunt provided a spur to the completion of a number of other
    projects, particularly the painting of the signal box, which had scaffolding
    round it, and the assembly of track in the North yard. A large contingent of
    volunteers turned out on the day, and Colin Fearnley filmed the event for
    posterity.

    Early in the morning we closed off Station Road, and the crane advanced with the
    second gate slung from its jib. Getting it to hang exactly right from the post
    took some care; the gate was roughly 26 feet long, weighed a ton, and the
    margin of error at the far end was about one inch. Once it was properly set,
    the fun started. So much stock had to be moved in such a small space that every
    working locomotive we possessed was in use, controlled by radios. Colin’s film
    shows six engines in action – Class 25, 08, Janus, Yellow Peril, Ruston 88DS
    and The Duke. The aim was a general shunt of the South and North Yards, plus
    the spreading of two trainloads of ballast, roughly 200 tons. We made full use
    of our opportunity and the shunting went on until after 9pm.

    We were a very happy band of lunatics in those days. One shot shows John Philips
    and myself with tinfoil on our heads. There was a reason for this. At that time
    there was a policy that photographs in the magazine must not show volunteers
    without hard hats, and these were painted in by the editor. The results were a
    little odd, and we looked as if we were going around with shiny blobs on our
    heads. This time John and I thought we’d save him the trouble.

    After the shunting we went back to our more mundane tasks. The platform work
    continued, and many dumper loads of spoil from this work were tipped on the
    lineside at the North end. The passenger entrance ramp was built and Mike
    Purslow put in a heroic amount of work to transform the area round it into a
    garden. This involved sieving many tons of muck to produce reasonably fertile
    soil; often he was still at it when we came back from the pub.

    The level crossing was ready for testing by the beginning of June. In signalling
    parlance, it was manually operated, mechanically locked and electrically
    detected. Trials took place on Sunday 2nd June, and these showed that road
    closures should be no more than three minutes each. The original target for the
    single track barrier crossing was two minutes. We also dropped another 160 tons
    of stone in the platform. All this stone and much more was arranged by John
    Allerton. This end of the railway, though far from finished, was now definitely
    under control and the remaining jobs were being steadily completed – gates
    painted, lighting columns erected, drains and fencing finished off. The gate
    lights were wired in and the specially made red targets arrived. Mike Hancox
    and his building team had the toilets structurally complete and were beginning
    to fit out the inside.

    At this time working on the railway was a communal activity, and it was quite
    normal for every compartment in the sleeping coach to be occupied, plus various
    odd bodies sleeping in the signal box, the station building and other odd
    corners. As we stoked our barbecues on the platform, the evidence of rapid
    progress was all around us.

    The influx of rolling stock continued, and a couple of Mark II coaches arrived
    at about this time. To create more space, we built a “blind siding”. There was
    just enough room alongside the feed mill to build a further siding on the down
    side of the South Yard. It was long enough for five or six carriages, and was
    filled with long term restoration projects. The main line was slewed to get
    them in rather than installing a set of points. The reasons for this were first
    of all to save the bother of installing another junction with the main line,
    secondly the clearance off the side of the feed mill was very tight, and if we
    had been able to shunt this would have created a potential hazard.

    One of the largest remaining projects was the construction of the run round loop
    and platform at Matlock Riverside. More sleepers were needed, so the salvage
    crew went back to Hams Hall where the Lichfield branch had been plugging away
    in our absence. Powergen were becoming very keen to have certain parts of their
    site totally clear, and I planned an intensive collection to take place midweek
    in September. I hired two tractors, six trailers and a crane. The aim was to
    set up a shuttle, each tractor would take a loaded trailer up to Darley Dale,
    leave it to be unloaded, and come straight back for another. If all went well,
    we intended to load 20 tons of rail every two hours, for eight hours per day
    for three days. The loading team consisted mostly of myself, Bob Grange, Dave
    Ives and Sam Cotton, with help from Lichfield branch, and the four of us booked
    into a local pub.

    Mick Thomas was in charge of the unloading party, and I think it is fair to say
    he had doubts about our ability to shift so much rail so quickly. So did Bob,
    who had kindly offered to wring my neck if things went expensively wrong. The
    combined hire charge was about £3-00 per minute. I had spent a couple of
    Saturdays dragging rails into nice neat stacks, so that they could be loaded
    two or three at a time, and marking the centres with paint as an aid to
    craning, and I was fairly sure we could do it. Andy Wood was working with Mick,
    and around noon on the first day I gave him a message to pass on with
    considerable satisfaction. Reception was poor so I kept it short. “Convoy One
    loaded. ETA 1400 hours”.

    There was one hold up, which took a little diplomacy to resolve. I was asked to
    have a word with the power station manager who had serious concerns. “Mr Oaks,
    one of our pylons is missing.” Not exactly missing as such; it was back at
    Darley Dale. Next to the old concentration sidings was the line training
    school, and part of its stock in trade was a dismantled pylon which had been
    lying in the grass for a very long time. Nice thick galvanised L section steel
    in a variety of sizes, with holes punched in the ends and bags of nuts and
    bolts to suit. A real adult meccano set. I had been given permission to take it
    months before by the head of the training school, which was being closed down,
    but we hadn’t had the time and transport to get it away before this point, and
    I had taken an opportunity the week before to get the main legs away with a
    load of sleepers. Meanwhile the manager concerned had retired without telling
    any one about the pylon. Understandably perhaps, Powergen felt they still had a
    use for it, so we sent it back again. All that galvanised steel angle. It would
    have come in very handy for the turntable, the water tower and all sorts of
    future projects. If anyone ever does hear of a pylon being got rid of…

    Otherwise the job went as smoothly as these things ever do. The crane leaked
    hydraulic oil steadily, and I had to hire a third tractor unit to shunt
    trailers around at Hams Hall. At the end of three days we had got away roughly
    220 tons of rail, enough for 1500 yards of track, plus eleven sets of turnout
    components which were tricky to load, but very valuable. By Andy’s account
    Mick’s language was worth a guinea a minute, as fast as he cleared one load
    away, another turned up. There was a succession of neat stacks of rail on the
    Down side of the trackbed towards Church Lane. We threw a monumental party in
    the South Yard that Saturday to celebrate. I presented the barbecue chef with
    a new house speciality- Hams Hall crispy duck, which had flown into a pylon
    that day. He declined my offer. According to my diary, not much was done on the
    following Sunday morning.

    Afterwards the urgent need for clearance was explained. The power station staff
    scooped up all the old ballast off the concentration sidings, which was then
    spread and rolled near the coal tippers. Then the staff caravan club parked
    their caravans on it, scores of them.

    Quite suddenly the programme locked up. All at once we knew what we would be
    doing each weekend for several weeks to come, and everything had to be done in
    sequence and on time. 202 Field Squadron Royal Engineers (T.A.) were booked in
    over the weekend of 17/18th August 2001 to help rebuild the ex-Cheedale Halt
    platform at Matlock. In advance we had to recover sufficient sleepers from Hams
    Hall, cut into the existing single line at Matlock, install a turnout, build the
    platform line, ballast it and tamp and complete the fine alignment work as a
    guide to build the platform. Once all that was done, the track on bridge 35
    would have to come out for an indefinite period to allow contractors access for
    bridge repairs. There were no alternative options and no margins for delay.
    Well, we did it. The T.A. came and camped in the South Yard and built 100 feet
    of the platform structure in a weekend.

    The design of the platform at Matlock Riverside is perhaps worth a look. I think
    it was originally invented by Martyn Ashworth, and refined slightly on the
    advice of the T.A. engineers. It can be constructed very quickly, and is just
    about idiot proof. The basic component is a trestle. First get yourself a
    circular saw, plenty of railway sleepers and a large quantity of threaded steel
    bar, to be cut to make bolts as required. Slice one sleeper in half, and another
    lengthways down the middle. Two halves of a sleeper make the uprights, joined by
    one sleeper across the bottom, and two across the top, on either side of the
    uprights. One half of the sliced sleeper is bolted to the rear upright, and
    this makes both a post for the back fence and a lever for lifting the trestle
    vertical. Paint all cut ends with preservative.

    The trestle will be roughly 4’2” tall with the boarding on top, and the top
    surface must be exactly 3’ above rail level, so if you dig a paving slab into
    the ballast, a bit below sleeper bottom level, this is going to be pretty
    close. If in doubt, dig down a bit more. The slabs go in one sleeper length
    apart. Stand up a pair of trestles, and nail three sleepers across the gap, one
    each side and one in the middle. Add a diagonal brace at the rear, and keep
    going down the line of the platform. Drill for additional bolts to fix the side
    sleepers to the uprights. The platform structure can be levelled with a template
    off the track, so the accuracy of the individual trestles is not critical. Just
    jack up the front of the trestle and add packings underneath, and then cross
    level to the rear and pack that in turn. Once the basic trestles are prepared, a platform can be built very quickly.

    Eventually we had the main structure complete and set about adding the top,
    which is mostly made of second hand floor joists. The timber in these is
    often of better quality than any new timber at anywhere near the price. A
    small gang set to work with hammers, and if I remember correctly this included
    Mick Bond, Bob Grange and Tony Joyce. One man set the sleepers out, and the
    other three each worked down one of the lines of supporting sleepers knocking
    in the nails. We had got quite a rhythm going, with three hammers marking time,
    and it looked as if we might get all the available boards on in one day. Only
    one problem, not enough nails, and by lunchtime we were running low. It was
    Sunday.

    This couldn’t be allowed to spoil a good day, so I drove over to Chesterfield
    where the local branch of a national DIY chain was open. There I collared an
    assistant near the nail section. There were large bins full of nails which had
    to be weighed out by staff.

    “Have you got any large unopened drums of five inch nails in stock?” He went off
    to make enquiries.

    “No”

    “Have you got a weighing machine which weighs out more than one pound?” He began
    to look a little worried, I think he saw where I was leading. Once more he went
    off, and returned distinctly unhappy.

    “No”

    “Well, I would like to buy fifty pounds weight of five inch nails, please”

    “You wouldn’t like to b*****r off and buy them some place else?”

    “No.” It took him quite a while to weigh them all out, but by the end of the day
    there were very few left. Originally this platform was to be called Matlock
    North, but watching the water go by as we built the platform, I had the idea
    that “Matlock Riverside” might be a better commercial proposition, and this was
    adopted.

    By now the tamper was working, and we set about the repetitive task of
    ballasting tamping and boxing in from Darley Dale southwards. The tamper was an
    absolute godsend, and produced a very high standard of track, which we simply
    could not have done manually. The other remaining major project was the
    footpath fence, which was a condition of our lease and was built by
    contractors.

    We were itching to run trains, for crew training and experience as much as
    anything else, and began a push pull service in December 1991. This ran from
    Darley Dale to Bridge 38, starting on one of the foggiest days I can remember.
    Beyond this point the line remained under engineers possession, and ballasting
    and tamping continued. Also about this time we built a workshop in a double
    garage in the south yard. It was intended as a very temporary stopgap at the
    time. The story of our efforts to design and build a more efficient facility
    over the intervening sixteen years would be a complex story in its own right.

    Salvage operations at Hams Hall continued. From time to time we would recover
    chairs, up to thirty tons in the course of a Saturday morning. We would hire
    ten ton tippers from Matlock Transport, and throw 500 chairs on each as they
    were driven slowly along the dismantled track. Bob Grange and Tony Joyce were
    regular passengers in my car for these trips, and one frosty winters morning
    there was laughter and happy glugging noises from the back. They had found my
    special bottle of Sheep Dip Whisky, well it kept the cold out.

    I booked a final midweek expedition to the power station in March 1992. We were
    under pressure to complete, as the site was to be redeveloped as a Channel
    Tunnel freight terminal. Another three days, another 200 tons of rail, with all
    the preparation work that implies. By now the transport budget was all but
    exhausted, and we were seriously short of space to put the stuff. I invited a
    couple of other railways to help themselves to the leftovers. I needed to clear
    out the permanent way stores hut as Messrs. Wood and Brandon had orders from
    Mick Thomas to recover the structure to provide materials for the crossing box
    at Darley Dale. One of the remaining items inside was a rail saw. Our guests
    from one railway were quite ecstatic.

    “Oh look – a hand operated rail saw!”

    I remembered so many past battles, and thought how far we had come. Watching
    the newcomers, who were good lads but inexperienced, I realised what a hard
    bitten and well drilled team we now had.

    “ You take it lads, I think you need it more than us”.

    The railway was opened to Matlock on 2nd May, 1992, by His Grace the Duke of
    Devonshire. I felt it was time for a break. There was a very good team in
    charge of construction – Mick, Bob, Gary Dixon, Chris Richardson and others, I
    was hardly indispensable, and I would have done my work very badly if I was. I
    resigned from the Peak Rail board in June 1992 and resolved to concentrate on a
    normal domesticated life. I was never cut out for that, and my absence did not
    last, but that is another story.

    Tim Oaks
     
  2. Johnny_Cash

    Johnny_Cash New Member

    Înscris:
    17 Iul 2008
    Mesaje:
    170
    Aprecieri primite:
    1
    Tim, I have just read all 5 of your long posts this evening. I have found them extremely interesting, very well written and they highligh the difficulties that new railways face when trying to establish themselves.

    I hope to read more of your experiences in the future.
     
  3. Woodster21

    Woodster21 Member

    Înscris:
    4 Feb 2007
    Mesaje:
    461
    Aprecieri primite:
    50
    Locație:
    Derbyshire
    Sadly i was the one that had to taken the pylon back! Hams Hall was also the location of being chased by the security staff as "someone" had forgotten to tell them that there would be a small 7.5t truck picking up smalls etc.

    One other point to mention when the TA arrived at Darley Dale Station they held a court martial for a driver (a woman by the way) who had hit a civilians car in Liverpool - now that was a sight
     
  4. sleepermonster

    sleepermonster Member

    Înscris:
    19 Iun 2007
    Mesaje:
    953
    Aprecieri primite:
    1.094
    The security staff had it in for us generally as they used to demolish the track on overtime at weekends before we arrived. Hams Hall was a funny place - part power station, mostly country park. I wandered into a building up nearr the coal tipplers one day, in case there was anything to be sniffed out when, this bloke popped up and said, "you can't come in here - this is the beekeepers stores"!

    Tim
     

Distribuie pagina asta