NYMR Winter Civil Engineering

Discussion in 'Heritage Railways & Centres in the UK' started by Ploughman, Feb 24, 2012.

  1. Ploughman

    Ploughman Part of the furniture

    Joined:
    Apr 1, 2008
    Messages:
    5,973
    Likes Received:
    2,763
    Occupation:
    Ex a lot of things.
    Location:
    Near where the 3 Ridings meet
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    A photo gallery of progress on the main civils projects being undertaken this winter on the NYMR can be seen at:-
    York Area Group

    Projects this year are
    Levisham North Relay - 16 length reballast and increase of sleepers from 24 to 28 per length.
    Newbridge relay - 12 length relay with F27 concrete sleepers and new FB113 rail.
    Reclipping at Beck Hole and Summit.
    Br 7 replacement in Pickering Station Reason why only a DMU service over half term.
    Trout Farm Crossover replacement with brand new FB 113 Vertical layout.

    More photos added on a regular basis.
     