@northernsteam To clarify the situation with the frame extension components. The outstanding component to allow the frame assembly to be...
The extra delay is only due to engineering lead times. The frame extensions are already on stock and the drag box is the only component that...
The latest news regarding the frame assembly is now available on our website. This represents a significant step towards having the frames...
Hi Aron The bag of bolts appeal is going very well. We are nearly half way through in terms of bolts sold. Bolts can be bought either as sets or...
Engineering update 7th March 2016 Another busy week on the engineering front. The sand printed mold for the exhaust steam spider is due to be...
We have scoured every available drawing and document and no mention has been found of double chimney Clans. I must admit, and not wishing to stir...
Yes this is very true. The Clans seemed to have gained a 'Marmite' reputation during their working days, crews either loved them or hated them....
A lot of the reports about the Clans were from crews of Brits who were used to Brit duties. The locos may have looked very similar but with the...
As a charity and as a duty of care to our members we must put such large contracts out to tender. There are now quite a few places capable of...
An update at last! Despite the seemingly quiet period we have been busy behind the scenes. On the engineering front the Trailing Keep Feet...
A very good question huochemi. You become a member of the Standard Steam Locomotive Company Ltd. "THE CLAN PROJECT" is the trading / brand name....
It may appear quiet, but like a graceful swan gliding over the water we are working madly behind the scenes. Not only are we waiting for parts but...
Why have PR Sold Zebedee? Surely that's going to reduce their number of available steamers albeit Zeb needed an overhaul
Thanks Sean A quick correction its AST T. Advanced Steam Technology Trust :)
The news article is now live on the website alongside the rendering